Bij brief van 2 januari 2019 schreef de gemachtigde van [naam] Holding aan CPD:
[naam] Holding has informed me that you are in breach with your obligations under the agreements. Most notably, you have failed to complete the project within the agreed period, thereby forfeiting the penalties provided for in the agreements. As to date, inter alia, the following work still needs to be completed:
i. The main stairs and ramp must be installed.
ii. The roof rain water drainage is defected and must be corrected.
iii. The work on the metal stairs to the secondfloor needs to be completed. This includes filling the gap on the stairs, attaching the stairs to the groundfloor and installing the side rails.
iv. The defective masonry works (as indicated by [naam 3]) must be corrected. We note that the subcontractor engaged by you to correct the masonry had ceased all work, apparently due to the fact that you have failed to fulfil your payment obligations to him.
v. The outstanding points on the punch list provided to you by [naam] must be completed.
vi. Upon completion of the above points, the building site must be cleaned.
(…)
On behalf of [naam] Holding, I herewith request CPD, and to the extent necessary I summon CPD to have completed all outstanding work (which includes remedying all defective work) ultimately on 25 January 2019 at 17:00.
Should you fail to comply with this demand, [naam] Holding reserves the right to (partially) terminate the agreements and to have the work completed by a third party. All costs associated therewith will be claimed from you. [naam] Holding furthermore explicitly reserves the right to claim the penalties incurred by CPD as a result of the late completion of the project and all damages that [naam] Holding has and will incur as a result thereof (…)